Bhubaneswar, 26 November 2026

General Manager, Shri Parmeshwar Funkwal, carried out a window trailing inspection of the Bhubaneswar–Daspalla section today. He conducted a detailed inspection of the Daspalla–Buguda section of the Khurda Road–Balangir New Railway Line by motor trolley and reviewed the progress of various works.

During the inspection, the General Manager reviewed the progress of various infrastructure works, including major bridges, tunnels, track formation, ballast and other associated railway infrastructure.

The inspection focused on the overall progress of the new railway line project and ensuring timely execution of the works. Shri Funkwal further emphasised on adhering to prescribed safety standards while expediting the ongoing works.
Chief Administrative Officer (Construction), Bhubaneswar, and Divisional Railway Manager, Khurda Road, accompanied the General Manager during the inspection.